Three-Phase Heating Element Replacement at Imperial College London View full image

Three-Phase Heating Element Replacement at Imperial College London

Published 21 Oct 2026Updated Wednesday, October 21, 2026
At a glance
Three-phase heating element replacement at Imperial College London for Dalkia, completed in a day with BMS integration and 60°C control signal wiring.
Status
Complete
Duration
1 day
Main client
Imperial College London
Sector
University / Education
Principal contractor
Dalkia

Project overview

Imperial College London required the replacement of an existing three-phase electric heating element connected to its Building Management System (BMS). The work was carried out on behalf of principal contractor Dalkia.

The hot water storage tank was drained before the existing element assembly was removed. A new three-phase element was installed, with the connections prepared and sealed before the electrical wiring was completed.

The replacement was connected to the existing supply and BMS. Additional control wiring provided a cut-out signal at the specified water temperature of 60°C, allowing the BMS to respond to that limit.

The completed installation

The heating element replacement and associated wiring were completed within one day. The work restored the system’s heating functionality and connected the replacement element to the existing BMS control arrangements.

The installation brought together the heating equipment, three-phase supply and temperature-control wiring, including the dedicated 60°C signal connection.

Project highlights

Tank draining & preparation

  • Draining the hot water storage tank before removing the existing heating element assembly.

Heating element replacement

  • Installing a new three-phase electric heating element.
  • Preparing and sealing the element connections for a secure, watertight installation.

Electrical connections

  • Connecting the replacement element to the existing three-phase electrical supply.

BMS integration

  • Connecting the heating element’s control arrangements to the existing Building Management System for temperature monitoring and control.

60°C control signal

  • Installing additional control wiring to send a cut-out signal to the BMS at the specified 60°C setpoint.

One-day programme

  • Coordinating and completing the replacement, electrical connections and control wiring within one day.
ON SITE

Project film

Silent playback
0:00

FAQs

What work was completed at Imperial College London?
The hot water storage tank was drained and the existing heating element assembly was replaced with a new three-phase element. The work included sealing the connections, completing the electrical wiring and connecting the control arrangements to the existing BMS.
How was the replacement heating element connected to the BMS?
The replacement element’s control arrangements were connected to the existing Building Management System to support temperature monitoring and control. Additional wiring provided a signal at the specified 60°C setpoint.
What was the purpose of the 60°C signal connection?
The additional control wiring provided a cut-out signal to the BMS when the water temperature reached the specified 60°C setpoint, allowing the BMS to respond to the temperature limit.
How long did the project take, and who was it carried out for?
The replacement and associated electrical and control wiring were completed within one day at Imperial College London, on behalf of principal contractor Dalkia.